Excavation within the original Scope Of Work is complete.
The Board is considering adding an additional 10 (+-) out of scope lights which will require additional excavation. Board Notice-To-Proceed is pending.
Working on the overhead service continues.
Park is completing the 4 inch water-main next week.
Park electrical trenching will be completed 2-3 work days.
Next two weeks will be the installation of disconnects.
Pulling cable is scheduled to begin/completed in 3-4 weeks.
Clean-up is weather dependent.